Full Timeline / Schedule

Below is a summary of the six projects’ milestones and deliverables. The overall schedule remains a work in progress and will be amended as needed based on thorough review of each project. Individual project schedules can be found under each school.

Priority One Timeline

The following is a general timeline outlining milestones leading up to the Priority One Projects. For more milestones specific to each Priority One school, please access the timeline under each school.

1999 - 2004
  • 1999 New England School Development
    Council long-range school facilities planning
  • 2000 Parsons Brinkerhoff, CMK Architects, and
    Lauer Architects facilities audit of Manchester
    Schools
  • 2004 New England School Development
    Council long-range school facilities planning report
2018 - 2020

CMK Architects long-range facilities plan District Strategic Plan adopted MGT Consulting capacity/utilization report

2021
  • Davis Demographics student forecast
    2020-2030
  • MGT Consulting capacity/utilization
  • Facilities (initial) recommendations
  • Hallsville Elementary School closes
  • Community forums on facilities
    recommendations
2022

Long-term facilities update

April 2023

SMMA engaged as the designer for the School
Facility Planning and design

November – December 2023

Priority One recommendations issued
Priority One Projects approved by Board of
Mayor & Aldermen

February 2024
LeftField is engaged as the Owners Project Manager
Individual School Timelines are available on each school page
Bobcat mascot
Beech Street elementary school
Panther mascot
MCLAUGHLIN Middle School
Hillside Eagle mascot
Hillside Middle School
Parkside Knights symbol or seal
Middle School at Parkside
Southside Spartans logo
Southside middle school